Name of Project : External structural repairs and restoration to LIC Jeevan Jyot Building at Napeansea Road. Mumbai
Client : Life Insurance Corporation (LIC)
Owner : Life Insurance Corporation (LIC)
Cost of Project : 1.82 Crs.
Time Taken for Completion of Project : 18 Months
Scope of Work
  • LIC staff Quarter more than 38 years old RCC building. Badly affected due to heavy leakages, corrosion of reinforcement, Spall of concrete, Damaged Chajjas and mainly not qualifying for current seismic code requirements. LIC decided to upgrade the structure as per the requirements of current seismic code.
Major Issue
  • Building cannot be vacated as at any given time the occupancy was at least 70 to 80 %.
Repair Technology:
  • Polymer Modified Mortar were used to rebuild damaged RCC section up to 25 to 50 mm
  • Micro concrete were used to rebuild damaged RCC section up to 50 to 100 mm
  • Seismic Retrofitting work was carried out by Jacketing External Columns and Beams
  • Seismic Retrofitting work was carried out by FRP Wrapping.
 
Name of Project : Internal Structural repairs, renovation & electrical works at flat 3B, 4B, 5B, & 5C Jeevan jyot building, Nepeansea Road, Mumbai.
Client : Life Insurance Corporation (LIC)
Owner : Life Insurance Corporation (LIC)
Cost of Project : 0.81 Crs.
Time Taken for Completion of Project : 10 Months
Scope of Work
  • Residential Quarters (4 Flats), of LIC. Buildings were not in sound conditions as they were badly affected due to heavy leakages, corrosion of reinforcement, Spall of concrete, Damaged Chajjas and the internal existing flooring, Plumbing and Electrical work were needed to be upgraded for the purpose of Flats being upgraded.
Major Issue
  • Flats occupancy was 100 %. Alternative arrangements were made for users and wing wise, building wise work was carried out as internal and external services had to be replaced.
Repair Technology:
  • Polymer Modified Mortar were used to rebuild damaged RCC section up to 25 to 50 mm
  • Micro concrete were used to rebuild damaged RCC section up to 50 to 100 mm
  • Old flooring replaced by Vitrified tiles
  • Old Mosaic dados were replaced by Ceramic tiles
  • Old Kitchen Platform replaced by Granite Platforms
  • Old Door were replaced by Flush Doors with Laminates and New Teakwood Frames
  • Old Paneled Windows were replaced by Anodized Aluminum Window
  • Old Internal & External Plumbing was replaced with CPVC,PVC and Lavish Jaguar CP Brass Fittings
  • Old Internal & External Electrical wiring, Switches, DB’s, fitting etc were replaced by new one’s of Brand Polycab, Precesion, Legrand, Havells, Crompton etc.
  • Internal Plastic Emulsion & External Anti Carbonation Painting
 
Name of Project : Structural Repairs to the Building Padmashali CHSL "C" & "D",”F” & “G”,”H” & “I” Wing Constructed under PMGP at Dharavi, Mumbai.
Client : The Maharashtra Housing & Area Development Authority (MHADA)
Owner : Padmashali Co-op Housing Society Ltd.
Cost of Project : 0.99 Crs. (Revised 2.98 Crs.)
Time Taken for Completion of Project : 18 Months
Scope of Work
  • Residential Building more than 38 years old RCC building. Badly affected due to heavy leakages, corrosion of reinforcement, Spall of concrete, Damaged Chajjas and mainly not qualifying for current seismic code requirements. Mhada decided to upgrade the Society structure as per the requirements of current seismic code.
Major Issue
  • Building cannot be vacated as at any given time the occupancy was at least 70 to 80 %.
Repair Technology:
  • Polymer Modified Mortar were used to rebuild damaged RCC section up to 25 to 50 mm
  • Micro concrete were used to rebuild damaged RCC section up to 50 to 100 mm
  • Seismic Retrofitting work was carried out by Jacketing External Columns and Beams
  • Seismic Retrofitting work was carried out by FRP Wrapping
 
Name of Project : Structural Repairs to the Building Mahatama Gandhi CHSL Bldg No. 5, 6 Constructed under P M G P at Dharavi, Mumbai.
Client : The Maharashtra Housing & Area Development Authority (MHADA)
Owner : Padmashali Co-op Housing Society Ltd.
Cost of Project : 1.23 Crs. (Revised 2.41 Crs.)
Time Taken for Completion of Project : 18 Months
Scope of Work
  • Residential Building more than 39 years old RCC building. Badly affected due to heavy leakages, corrosion of reinforcement, Spall of concrete, Damaged Chajjas and mainly not qualifying for current seismic code requirements. Mhada decided to upgrade the Society structure as per the requirements of current seismic code.
Major Issue
  • Building cannot be vacated as at any given time the occupancy was at least 70 to 80 %.
Repair Technology:
  • Polymer Modified Mortar were used to rebuild damaged RCC section up to 25 to 50 mm
  • Micro concrete were used to rebuild damaged RCC section up to 50 to 100 mm
  • Seismic Retrofitting work was carried out by Jacketing External Columns and Beams
  • Seismic Retrofitting work was carried out by FRP Wrapping
 
Name of Project : Structural Repairs to the Building Kshetrapaleshwar CHSL, Bldg. No. 29 & 30, 31 & 32, 44 & 45 Constructed under P M G P at Dharavi, Mumbai.
Client : The Maharashtra Housing & Area Development Authority (MHADA)
Owner : Kshetrapleshwar Co-op Housing Society Ltd.
Cost of Project : 1.71 Crs. (Revised 3.04 Crs.)
Time Taken for Completion of Project : 18 Months
Scope of Work
  • Residential Building more than 34 years old RCC building. Badly affected due to heavy leakages, corrosion of reinforcement, Spall of concrete, Damaged Chajjas and mainly not qualifying for current seismic code requirements. Mhada decided to upgrade the Society structure as per the requirements of current seismic code.
Major Issue
  • Building cannot be vacated as at any given time the occupancy was at least 70 to 80 %.
Repair Technology:
  • Polymer Modified Mortar were used to rebuild damaged RCC section up to 25 to 50 mm
  • Micro concrete were used to rebuild damaged RCC section up to 50 to 100 mm
  • Seismic Retrofitting work was carried out by Jacketing External Columns and Beams
  • Seismic Retrofitting work was carried out by FRP Wrapping
 
Name of Project : Renovation & Repairs of Staff Quarters of ESIC Model Hospital at Andheri (E), Mumbai
Client : National Building Construction Corporation Ltd. (NBCC)
Owner : Employee State Insurance Corporation (ESIC)
Cost of Project : 4.30 Crs.
Time Taken for Completion of Project : 12 Months
Scope of Work
  • 5 Residential Quarters comprising of Type III Building no. 1 (G+4) (5 Flats) , Type III Building no. 2 (G+4) (20 Flats) , Type IV Building no. 3 (G+1) (4 Flats) , Type II Building no. 3 (G+4) (5 Flats), Type II Building no. 1 (G+4) (5 Flats) of ESIC Model Hospital. Buildings were not in sound conditions as they were badly affected due to heavy leakages, corrosion of reinforcement, Spall of concrete, Damaged Chajjas and the internal existing flooring, Plumbing and Electrical work were needed to be upgraded for the purpose of Hospital being upgraded to Post Graduate Collage
Major Issue
  • Flats occupancy was 100 %. Alternative arrangements were made for users and wing wise, building wise work was carried out as internal and external services had to be replaced.
Repair Technology:
  • Polymer Modified Mortar were used to rebuild damaged RCC section up to 25 to 50 mm
  • Micro concrete were used to rebuild damaged RCC section up to 50 to 100 mm
  • Old flooring replaced by Vitrified tiles
  • Old Mosaic dados were replaced by Ceramic tiles
  • Old Kitchen Platform replaced by Granite Platforms
  • Old Door were replaced by Flush Doors with Laminates and New Teakwood Frames
  • Old Paneled Windows were replaced by Anodized Aluminum Window
  • Old Internal & External Plumbing was replaced with CPVC,PVC and Lavish Jaguar CP Brass Fittings
  • Old Internal & External Electrical wiring, Switches, DB’s, fitting etc were replaced by new one’s of Brand Polycab, Precesion, Legrand, Havells, Crompton etc.
  • Internal Plastic Emulsion & External Anti Carbonation Painting
 
Name of Project : Seismic Retrofitting of MGM Hospital at Parel, Mumbai
Client : Hydroair Tectonics (PCD) Ltd.
Owner : Employee State Insurance Corporation (ESIC)
Cost of Project : 2.5 Cr
Time Taken for Completion of Project : 6 Months
Scope of Work
  • MGM (Mahatma Gandhi Memoriam) Hospital is more than 45 years old RCC building. Badly affected due to heavy leakages, corrosion of reinforcement, Spall of concrete, Damaged Chajjas and mainly not qualifying for current seismic code requirements. Being important public service building, ESIC decided to upgrade the hospital structure as per the requirements of current seismic code.
Major Issue
  • Building cannot be vacated as at any given time the occupancy was at least 70 to 75 %.
Repair Technology:
  • Polymer Modified Mortar were used to rebuild damaged RCC section up to 25 to 50 mm
  • Micro concrete were used to rebuild damaged RCC section up to 50 to 100 mm
  • Seismic Retrofitting work was carried out by FRP Wrapping
 
Name of Project : Seismic Retrofitting of ESIC Dental Collage & Hospital at Vashi, Navi Mumbai
Client : Uttar Pradesh Rajya Nirman Nigam Limited
Owner : Employee State Insurance Corporation (ESIC)
Cost of Project : 12 Cr
Time Taken for Completion of Project : 40 Months
Scope of Work
  • ESIC Dental Collage & hospital is more than 35 years old RCC building. Badly affected due to heavy leakages, corrosion of reinforcement, Spall of concrete, Damaged Chajjas and mainly not qualifying for current seismic code requirements. Being important public service building, ESIC decided to upgrade the hospital structure as per the requirements of current seismic code.
Major Issue
  • Building cannot be vacated as at any given time the occupancy was at least 70 to 75 %.
Repair Technology:
  • Polymer Modified Mortar were used to rebuild damaged RCC section up to 25 to 50 mm
  • Micro concrete were used to rebuild damaged RCC section up to 50 to 100 mm
  • Seismic Retrofitting work was carried out by Jacketing External Columns and Beams
  • Seismic Retrofitting work was carried out by demolishing and recasting the terrace level slabs
  • Seismic Retrofitting work was carried out by FRP Wrapping
 
Name of Project : Renovation & Repairs of Staff Quarters of MGM Hospital at Parel, Mumbai
Client : National Building Construction Corporation Ltd. (NBCC)
Owner : Employee State Insurance Corporation (ESIC)
Cost of Project : 6.7 Crs.
Time Taken for Completion of Project : 18 Months
Scope of Work
  • 3 Residential Quarters comprising of Building no. 1 (G+4) (16 Flats), Building no. 2 (G+5) (12 Flats), Building no. 4 (G+5) (35 Flats C Wing) of MGM (Mahatma Gandhi Memoriam) Hospital. Buildings were not in sound conditions as they were badly affected due to heavy leakages, corrosion of reinforcement, Spall of concrete, Damaged Chajjas and the internal existing flooring, Plumbing and Electrical work were needed to be upgraded for the purpose of Hospital being upgraded to Post Graduate Collage
Major Issue
  • Flats occupancy was 100 %. Alternative arrangements were made for users and wing wise, building wise work was carried out as internal and external services had to be replaced.
Repair Technology:
  • Olymer Modified Mortar were used to rebuild damaged RCC section up to 25 to 50 mm
  • Micro concrete were used to rebuild damaged RCC section up to 50 to 100 mm
  • Old flooring replaced by Vitrified tiles
  • Old Mosaic dados were replaced by Ceramic tiles
  • Old Kitchen Platform replaced by Granite Platforms
  • Old Door were replaced by Flush Doors with Laminates and New Teakwood Frames
  • Old Paneled Windows were replaced by Anodized Aluminum Window
  • Old Internal & External Plumbing was replaced with CPVC,PVC and Lavish Jaguar CP Brass Fittings
  • Old Internal & External Electrical wiring, Switches, DB’s, fitting etc were replaced by new one’s of Brand Polycab, Precesion, Legrand, Havells, Crompton etc.
  • Internal Plastic Emulsion & External Anti Carbonation Painting
 
Name of Project : Make up of lost strength of core concrete shall be with grouting of low viscosity Epoxy grout at Fonda, Goa
Client : Vascon Engineers Ltd.
Owner : Cipla Ltd.
Cost of Project : 5 Lacs.
Time Taken for Completion of Project : 1 Months
Scope of Work
  • Make up of lost strength of core concrete shall be with grouting of low viscosity (2-5cps as per ASTM-D-2196) monomer. This is a low viscous high molecular weight thermosetting polymer. Due to its low viscosity it effectively fills up all micro-cracks and voids up to full depth of concrete. Beside enhancing existing binding matrix this shall also enhance in ductility property of elements.
Major Issue
  • Cube Test and Pre NDT Test were failed and the consultant of owner wanted to make up the lost strength of core concrete without demolishing the slab.
Repair Technology:
  • Drilling Holes: Drilling 12 mm dia., 50 to 75 mm deep holes in structural members at the intervals of 350 mm in staggered manner or as directed by the consultants in RC structural element.
  • Cleaning of holes: Clean the holes by air blower prior to fixing nozzles. Fixing of Nozzles: Insert 12 mm dia. Teflon nozzles in cleaned holes. External end of nozzles to be machine to receive outlet of grouting gun. Fix it inside the holes by applying thixotropic epoxy putty to ensure complete sealing system for min. 12 hrs.
  • Cutting of Nozzles: Cut the nozzles by chisel after completion of grouting without damaging structural elements.
  • Injecting Chemicals: Injecting Monopol by pressure and using mechanized injector gun with accessories till nozzles refuses to accept the grout
  • Results: Post NDT results were surprising with 49 % increase in comprehensive strength of core concrete.
 
Name of Project : Repairs & Retrofitting of IGIB Building, Delhi University Campus, Delhi.
Client : Bharat Sanchar Nigam Limited (BSNL)
Owner : Bharat Sanchar Nigam Limited (BSNL)
Cost of Project : 2.32 Crs.
Time Taken for Completion of Project : 18 Months
Scope of Work
  • IGIB Building more than 40 years old RCC building. Badly affected due to heavy leakages, corrosion of reinforcement, Spall of concrete, Damaged Chajjas and mainly not qualifying for current seismic code requirements. BSNL decided to upgrade the IGIB structure as per the requirements of current seismic code.
Major Issue
  • Building cannot be vacated as at any given time the occupancy was at least 70 to 80 %.
Repair Technology:
  • Polymer Modified Mortar were used to rebuild damaged RCC section up to 25 to 50 mm
  • Micro concrete were used to rebuild damaged RCC section up to 50 to 100 mm
  • Seismic Retrofitting work was carried out by Jacketing External Columns and Beams
  • Seismic Retrofitting work was carried out by FRP Wrapping

 
Name of Project : Upgradation / Renovation of Parliament House Annexe Building New Delhi. Sh: Improvement of External Façade.
Client : Central Public Work Department (CPWD)
Owner : Parliament House
Cost of Project : 2.32 Crs.
Time Taken for Completion of Project : 18 Months
Scope of Work
  • Parliament House Annex Building more than 34 years old RCC building. Badly affected due to heavy leakages, corrosion of reinforcement, Spall of concrete, Damaged Chajjas and mainly not qualifying for current seismic code requirements. CPWD decided to upgrade the Annex structure as per the requirements of current seismic code.
Major Issue
  • Building cannot be vacated as at any given time the occupancy was at least 70 to 80 %.
Repair Technology:
  • Polymer Modified Mortar were used to rebuild damaged RCC section up to 25 to 50 mm
  • Micro concrete were used to rebuild damaged RCC section up to 50 to 100 mm
  • Seismic Retrofitting work was carried out by Jacketing External Columns and Beams
  • Seismic Retrofitting work was carried out by FRP Wrapping

 
Name of Project : Structural repairs to columns, south side shear wall, west side pavement slab and painting of Sanchar Bhawan, 20, Ashoka Road, New Delhi. (SH: Structural Repairs).
Client : Bharat Sanchar Nigam Limited (BSNL)
Owner : Bharat Sanchar Nigam Limited (BSNL)
Cost of Project : 4.27 Crs.
Time Taken for Completion of Project : 24 Months
Scope of Work
  • Sanchar Bhawan Building more than 37 years old RCC building. Badly affected due to heavy leakages, corrosion of reinforcement, Spall of concrete, Damaged Chajjas and mainly not qualifying for current seismic code requirements. BSNL decided to upgrade the Sanchar Bhawan structure as per the requirements of current seismic code.
Major Issue
  • Building cannot be vacated as at any given time the occupancy was at least 70 to 80 %.
Repair Technology:
  • Polymer Modified Mortar were used to rebuild damaged RCC section up to 25 to 50 mm
  • Micro concrete were used to rebuild damaged RCC section up to 50 to 100 mm
  • Seismic Retrofitting work was carried out by Jacketing External Columns and Beams
  • Seismic Retrofitting work was carried out by FRP Wrapping

 
Name of Project : Structural Rehabilitation, Repair & Renovation Works of Primary Block.
Client : Army Public School (APS)
Owner : Army Public School (APS)
Cost of Project : 5.21 Crs.
Time Taken for Completion of Project : 18 Months
Scope of Work
  • APS Building more than 32 years old RCC building. Badly affected due to heavy leakages, corrosion of reinforcement, Spall of concrete, Damaged Chajjas and mainly not qualifying for current seismic code requirements. APS decided to upgrade the Army Public School structure as per the requirements of current seismic code.
Major Issue
  • Building cannot be vacated as at any given time the occupancy was at least 70 to 80 %.
Repair Technology:
  • Polymer Modified Mortar were used to rebuild damaged RCC section up to 25 to 50 mm
  • Micro concrete were used to rebuild damaged RCC section up to 50 to 100 mm
  • Seismic Retrofitting work was carried out by Jacketing External Columns and Beams
  • Seismic Retrofitting work was carried out by FRP Wrapping