| Name of Project : | External structural repairs and restoration to LIC Jeevan Jyot Building at Napeansea Road. Mumbai |
| Client : | Life Insurance Corporation (LIC) |
| Owner : | Life Insurance Corporation (LIC) |
| Cost of Project : | 1.82 Crs. |
| Time Taken for Completion of Project : | 18 Months |
|
|
| Name of Project : | Internal Structural repairs, renovation & electrical works at flat 3B, 4B, 5B, & 5C Jeevan jyot building, Nepeansea Road, Mumbai. |
| Client : | Life Insurance Corporation (LIC) |
| Owner : | Life Insurance Corporation (LIC) |
| Cost of Project : | 0.81 Crs. |
| Time Taken for Completion of Project : | 10 Months |
|
|
| Name of Project : | Structural Repairs to the Building Padmashali CHSL "C" & "D",”F” & “G”,”H” & “I” Wing Constructed under PMGP at Dharavi, Mumbai. |
| Client : | The Maharashtra Housing & Area Development Authority (MHADA) |
| Owner : | Padmashali Co-op Housing Society Ltd. |
| Cost of Project : | 0.99 Crs. (Revised 2.98 Crs.) |
| Time Taken for Completion of Project : | 18 Months |
|
|
| Name of Project : | Structural Repairs to the Building Mahatama Gandhi CHSL Bldg No. 5, 6 Constructed under P M G P at Dharavi, Mumbai. |
| Client : | The Maharashtra Housing & Area Development Authority (MHADA) |
| Owner : | Padmashali Co-op Housing Society Ltd. |
| Cost of Project : | 1.23 Crs. (Revised 2.41 Crs.) |
| Time Taken for Completion of Project : | 18 Months |
|
|
| Name of Project : | Structural Repairs to the Building Kshetrapaleshwar CHSL, Bldg. No. 29 & 30, 31 & 32, 44 & 45 Constructed under P M G P at Dharavi, Mumbai. |
| Client : | The Maharashtra Housing & Area Development Authority (MHADA) |
| Owner : | Kshetrapleshwar Co-op Housing Society Ltd. |
| Cost of Project : | 1.71 Crs. (Revised 3.04 Crs.) |
| Time Taken for Completion of Project : | 18 Months |
|
|
| Name of Project : | Renovation & Repairs of Staff Quarters of ESIC Model Hospital at Andheri (E), Mumbai |
| Client : | National Building Construction Corporation Ltd. (NBCC) |
| Owner : | Employee State Insurance Corporation (ESIC) |
| Cost of Project : | 4.30 Crs. |
| Time Taken for Completion of Project : | 12 Months |
|
|
| Name of Project : | Seismic Retrofitting of MGM Hospital at Parel, Mumbai |
| Client : | Hydroair Tectonics (PCD) Ltd. |
| Owner : | Employee State Insurance Corporation (ESIC) |
| Cost of Project : | 2.5 Cr |
| Time Taken for Completion of Project : | 6 Months |
|
|
| Name of Project : | Seismic Retrofitting of ESIC Dental Collage & Hospital at Vashi, Navi Mumbai |
| Client : | Uttar Pradesh Rajya Nirman Nigam Limited |
| Owner : | Employee State Insurance Corporation (ESIC) |
| Cost of Project : | 12 Cr |
| Time Taken for Completion of Project : | 40 Months |
|
|
| Name of Project : | Renovation & Repairs of Staff Quarters of MGM Hospital at Parel, Mumbai |
| Client : | National Building Construction Corporation Ltd. (NBCC) |
| Owner : | Employee State Insurance Corporation (ESIC) |
| Cost of Project : | 6.7 Crs. |
| Time Taken for Completion of Project : | 18 Months |
|
|
| Name of Project : | Make up of lost strength of core concrete shall be with grouting of low viscosity Epoxy grout at Fonda, Goa |
| Client : | Vascon Engineers Ltd. |
| Owner : | Cipla Ltd. |
| Cost of Project : | 5 Lacs. |
| Time Taken for Completion of Project : | 1 Months |
|
|